At the last GSS Council meeting on July 23, 2009, a plan to expand Koerner's Pub came up for council approval. However, before it could be dealt with quorum was lost for the third month in a row and no decision could be made. This project has been on the table for quite a while now, and many people have put a lot of work into refining the design and financing options of the plan.
Most graduate students and other patrons of Koerner's Pub are unaware of the planned pub expansion. Since it represents one of the biggest and most meaningful projects the GSS has considered in a number of years, this post is meant to inform all of those people about what the project's all about, why it's worthwhile, and what the current situation is. Most of the information in here represent the findings of the Pub Patio Project Task Force (PPPTF) and its presentation to council, which can be viewed here.


Two views of the area that would be enclosed by the new patio.

Conceptual Rendering of glassed-in patio.
Capital Costs
Currently, the total cost of the project is about $177,000, broken down as follows:
$98,000 (due upon completion)
$41,000 (interest-free loan – to be paid to contractor $1,700/month for 24 months)
$38,000 (for Plant Ops electrical, plumbing, safety work; furniture and fixtures)
The project was actually ready to go last November but delays have pushed the cost of the project up more than $20K. The current quote is/was good until the end of July. The contractor is so keen to see the project go ahead they are willing to provide a $41,000 interest free loan to be paid off over two years.
Projected Revenues
Of course the underlying assumption with this project is that it would eventually pay for itself through increased revenues. Based on projections, it could add an extra $180,000 of revenue each year, resulting in an extra $50,000 in profit.
The assumptions made to arrive at this figure are that with the patio, Koerner's will get 25 more people (in the added 40 seats) for 2 hours during lunch time and 2 hours during dinner time for each of Monday, Thursday and Friday spending $10/hour. In other words and extra $125 spent in Koerner's per hour to 40 seats; or even simpler $3.15/seat/hour for meal times three days a week. If you've ever been to Koerner's on a Monday or Friday night, you know how busy it can get - this is not included in the estimate (neither are other days of the week) and therefore I think, and many agree, that the numbers are quite conservative.
The costs associated with providing the product these seats is 46% of the revenue and the cost of servicing these seats (2 extra staff and some other expenses) is 47% of the remainder. So of the revenue collected, 71% goes to cover costs; the rest would go either into paying down the cost of the expansion, or to profits. That's where the extra $50,000 comes from.
The payback period was also examined, and is simply the total cost of the project divided by the annual added income. Five years was identified as a suitable payback period, and the project should fall within this criterion. A best case scenario would see the patio paid off in 3.3 years and an absolute worst case scenario gave a payback period of 13 years.
Funding
The GSS is capable of paying for the whole project itself. Each year every graduate student pays a $5 fee for capital improvements (CPIF). Between the surplus from 2008 and the 2009 funds, there is $65,000 in CPIF funds available. General revenues for the GSS also had a surplus in 2008, from which up to $40,000 is available. That could cover the upfront $98,000 payment to the contractor.
The two-year $41,000 interest-free loan from the contractor could be paid off from extra pub revenues once the new patio is up and running. This leaves the GSS still short $35,000 on the project, but that could be paid for with a loan, more of the 2008 surplus (which was $69,000 in total), outside funding, or sponsorships.
This project may result in some short term cash flow problems, but all of the GSS's programs and services should remain unaffected. The GSS makes annual budget including all the annual projects, parties, events, etc the GSS puts on which would remain intact.
Current Situation
While council did have the opportunity to discuss the issue at the last meeting, the discussion got severely side-tracked by a lengthy Economics 101 lecture necessitated by a very few people at the meeting who either did not understand, or were presenting confusing information to council. These people were former and current executives. Although the GSS executives are against the project, council is ultimately the body to make this decision, a decision that will have to be made at some point. Too much work has gone into this plan from too many people for it to fail due to continued lack of quorum.